Calculation support, not a guaranteed safety decision.

Fire main acceptance testing pressurises large-diameter pipework, normally with water under NFPA 24. Air is only used as a cold-weather interim test and does not replace the hydrostatic test.

High-energy check

Treat the test as high energy along the whole main, not just at the pump. Thrust blocks and end caps are the main release points. If air is used for a cold-weather interim test instead of water, stored energy at the same pressure is far higher; use the pneumatic calculator to see the scale.

This task's main energy sources are not calculated by this tool. Use the trigger checks below and competent-person verification.

Estimate the stored energy if this test uses air

Trigger checks

Direct controls to verify

Ticks stay on this screen only. Nothing is saved or sent.

For your SPA or pre-start

State the test medium (water or air), the test pressure and extent, the exclusion along the route, the condition of end restraints and who authorises pressurisation.